The City of Winnipeg will be rehabilitating a segment of Pembina Highway between Confusion Corner and Grant Avenue in the coming years, which will allow for the addition of buffered bike lanes along with the rehabilitation of travel lanes and sidewalks. We see this as a positive step that will benefit all users of Pembina Highway, especially those of us who ride (or would like to ride) our bikes on Pembina.
It is important that plans for this rehabilitation project include cycling infrastructure that connects with existing as well as the planned cycling facilities such as:
- Nassau Street (Existing Neighbourhood Greenway)
- Warsaw Avenue (Existing Neighbourhood Greenway)
- McMillan Avenue (Planned Neighbourhood Greenway)
- Corydon Avenue
- Southwest Rapid Transit Corridor Multiuse Pathway (Existing)
- Pembina Highway Buffered Bike Lanes (planned as part of this project)
- Osborne Street Bike Lanes (planned through Osborne Underpass)
- South Winnipeg Parkway (existing, planned extension to Brandon Ave)
Please Attend the Open House to Discuss Options for Pembina
Winnipeggers are invited to an open house to view the proposed design for the rehabilitation of Pembina Highway from Osborne Street to Grant Avenue. There will be an opportunity to ask questions and provide feedback.
Date: April 21, 2016
Time: 4:00 p.m. – 7:00 p.m.
Location: River Osborne Community Centre, 101 Pembina Highway
For more information, or if you are unable to attend the open house and would like to provide feedback, you can visit the project wesbite at www.winnipeg.ca/PembinaRehab. You can review the presentation boards here.
Bike Winnipeg Recommendations
After reviewing the plans that will be presented at the Open House for this project on April 21st, Bike Winnipeg has come up with the following recommendations to improve these draft plans.
Recommendation #1 – Maintain Crossing of Pembina at Corydon
We are concerned that the plans to eliminate the crossing of Pembina on the separator island eliminate a useful connection between destinations north of Corydon and South Osborne.
Currently, a person biking from north of Corydon headed towards south Osborne has the ability to approach Pembina on Corydon and cross Pembina within one traffic signal phase so that they can reach the corner of Pembina & Osborne in time to turn right when the signal at Pembina and Osborne turns green for southbound traffic crossing Osborne. This creates a good lead time for a person biking south through the Osborne Underpass as southbound traffic on Osborne will be stopped at a red light.
The proposed redesign of the island separating northbound traffic from eastbound and southbound traffic on Osborne/Corydon will prevent a person on bike from making the turn onto southbound Osborne until southbound traffic on Osborne gets the green light, removing the lead time they have that currently allows them to get through the Osborne Underpass ahead of southbound traffic.
Similarly, anyone who is trying to connect to the pathway along the south side of Donald will have to wait for traffic on Osborne to stop before reaching the two way cycle track along the south of Corydon that parallels the transitway, resulting in a significant delays and a reduced level of service.
Recommendation #2 – Develop a Connection to McMillan
Winnipeg’s Pedestrian & Cycling Strategies identify McMillan Avenue as a future neighbourhood greenway on the north side of Corydon connected to confusion corner via a pathway through the River-Osborne Community Centre site.
Recommendation #3 – Improve Separation Between Bikes and Bus Patrons
While we agree with the decision to route the bike lane behind the bus stops, we feel that a number of improvements could be made to the design to improve separation between people biking on Pembina and those getting on or off of buses.
In particular, we would prefer to see the bike lane by-passes around the bus stops kept at street level (or midway between street level and sidewalk level) as is done on Sherbrook Street. This will increase the differentiation between pedestrian and bicycle areas behind the bus stop.A sidewalk connection to the bus platform can be raised. Additionally,poles with hanging planters could be used to help define boundaries of the bus platforms, and would provide aesthetic benefits as well.
See the examples below, taken from the Massachusetts Planning & Design Guide for Separated Bike Lanes.
Recommendation #4 – Plan for Left Turns onto Daly
We’d like to see a left turn storage bay installed on the east side of Pembina to help facilitate two stage left turns off of Pembina onto Daly at the existing half-signal pedestrian crossing.
People on foot should be separated from people on bikes at this crossing, and there would need to be a way for people on bikes to activate the signal from their bikes.
On the west side of Pembina, we suggest adding separator islands to protect people on bikes from right/left turning vehicles. This is especially important on the north side of Daly as vehicles turning left off of Pembina will be separated from bikes turning left off of Pembina if the bike lane follows just south of the pedestrian crosswalk.
Recommendation #5 – Improve Safety at Grant Intersection
We are concerned that the wide radius on the merge lane from Pembina onto Grant presents a right hook threat to people on bikes, and would like to see the turning radius tightened up to reduce the speed of turning vehicles. Ideally, we would like to see something similar to a protected intersection treatment used here, where the buffered bike lane is bent out from Pembina before crossing the Grant Avenue merge lane at a right angle. This would force vehicles to slow down before crossing the bike lane and crosswalk, providing much better sight lines for all users of the intersection and would improve overall safety.
Recommendation #6 -Widen Bike Lanes to Improve Comfort Levels
We feel that lane widths on Pembina can be reduced to allow for a wider bike lane. See Theo Zeegers research document that underlies the CROW and MASSDOT Separated Bike Lanes Planning & Design Guidelines.
Narrower travel lanes could be used – there is plenty of guidance in support of narrower lanes.
- See NACTO Urban Street Design Guide advice on lane widths
- See MAP 21 – NHS Impact – AASHTO Standards – Lane Width/Truck Volume Guidance
- See Bellefleur, O. (2014). Traffic Lane Width of 3.0 m in Urban Environments. Montreal, Quebec: National Collaborating Centre for Healthy Public Policy.
Recommendation #7 – Consolidate Access Points along Pembina
To improve both walking and biking conditions along Pembina, a reduction in the number of access points (or at least measures to shorten the crossing distance at access points), should be considered. For example, access to Garwood might be removed (or made one way) in favour of access from Daly).
The skewed angle of Garwood in the image shown above is a good example of an excessively long crossing distance for people walking or biking along Pembina. Where access points are closed or narrowed, planters could be added to improve aesthetics along Pembina.
Do we really need two way access to Garwood and Daly from Pembina?
Recommendation #8 – Improve Access to Osborne Station
As the current access to Osborne Station from the east side of Osborne is via sidewalk from Corydon or through the Masonic Lodge parking lot, it would be good to see a pathway connection from the Osborne Station to the Southwest Rapid Transit Corridor AT path included as part of this project.
As shown below, there should be enough space between the transitway and parking lot to provide this connection, which would reduce conflict between people on bike and foot.
Additional Resources
City of Winnipeg Pembina Highway Rehabilitation Project Website Portal
Guides
Massachusetts DOT Separated Bike Lane Planning & Design Guide
Alta Planning + Design – Lessons Learned: Evolution of the Protected Intersection